The work schedule shows one week at a time, with a row per employee and a column per day. Each shift is shown as a bar placed by time of day, so you can quickly see who starts early and who closes. Only owners and admins can create and change the schedule.
Step by step
- Go to "Work schedule" in the menu under "Time tracking", and choose the "Planning" tab.
- If you have departments, choose the schedule in the cards at the top: "Shared schedule" or a department.
- Find the week you want to plan with the arrows next to the week number.
- Click the cell for the employee and the day. The start time is filled in with 08:00, and the end time matches the employee’s usual hours that day.
- Adjust "Start" and "End" as needed. The duration is shown below the fields.
- If the employee has the same shift on several days, select the days under "Days". Existing shifts on the selected days are replaced.
- Press "Save". The shift now appears in the week view.
Keeping track of the hours
Under each employee’s name you see the hours they have been given that week next to their weekly working hours, e.g. "30 / 37 h". The top of each column shows the total planned hours for that day, and the bottom shows the total for the week.
Employees on vacation
If an employee has registered vacation, the cell for that day says "Vacation". If the vacation hasn’t been approved yet, it says "Vacation · pending" with a dashed border. An employee on vacation can’t be given a shift that day – not through "Days" or by being given an open shift either. Rejected vacation doesn’t count.